The standing set for the Linear project: the outcome and the territory, the calls that bind more than one epic, the rules every epic obeys with owners, and the arc. Absorbed from the project's existing Linear content (6,060 chars) rather than written fresh — the substrate/convention test, the Layer 1/Layer 2 split, the agents-as-humans framing and the settled renames were all already there with nowhere above one epic to live. Nothing was dropped as stale; the vocabulary manifest stays in Linear as the reference list it is. Two things the set records rather than tidies: FIX-1359 is marked done with 7 of 11 issues closed, and 32 of 65 work issues sit under no epic at all — the vocabulary era the project began in. Both are the useful signal. PR-4 carries the W3 correction in its general form — every derived key is refused, not the one key found first — because the original seven-rule table rotted exactly once already. One open question, verified not assumed: rooms have no declaration surface (`RoomManifest|createRoom|roomRegistry|defineRoom` → 0 matches across packages/), while FIX-1352 describes them as written in code. It binds W3 and W4, so it is recorded as an ask rather than answered here. Figures rendered in both themes before commit; the arc lost its dashed not-started bars, which read as duration. Verify: fences even, no risky mermaid labels, both SVGs self-contained with aria-labels and under 70 lines, budgets 572/799/502/444 against 700/900/600/700. Co-Authored-By: Claude Opus 5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_01MpacHaJN9Rba13WrsPJosZ
|
The latest updates on your projects. Learn more about Vercel for GitHub. 3 Skipped Deployments
|
Process guards failed here for the reason the machinery PR fixes: the exemption is keyed on branch name and main's copy lists only spec/* and epic/*, so a project/<slug> branch carrying spec/_projects/<slug>/ is checked and fails. The fix is already on #1816. Ported verbatim rather than waiting for that to merge; it no-ops the moment main carries it. This branch never merges, so the duplicate hunk dies with it. Co-Authored-By: Claude Opus 5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_01MpacHaJN9Rba13WrsPJosZ
|
The two <img src="````https://raw.githubusercontent.com/fixpoint-labs/flow-state-dev/c0dfaff7daf3e8e6ef364d5a712680e84acf47a1/spec/_projects/workforce-layer-2-abstraction/figures/territory.svg"```` width="940" alt="The territory: Layer 2 conventions owned here, the Layer 1 substrate assembled but owned elsewhere, and Task/Skills/Memory implementation outside the project. The fence is one test: is there exactly one of it?" /><img src="````https://raw.githubusercontent.com/fixpoint-labs/flow-state-dev/c0dfaff7daf3e8e6ef364d5a712680e84acf47a1/spec/_projects/workforce-layer-2-abstraction/figures/arc.svg"```` width="940" alt="The arc: five epic lanes across ten days. W2 ran Sep 8 to Sep 12, done. The default agent flow ran Sep 12 to Sep 16, done. W3 started Sep 16 and is in flight at the now line. W1 and W4 have not started." />Both URLs serve What happened, since it's worth recording. Your note about backticks in the I tried to fix them by rewriting the body, which was the wrong call and broke more than it fixed. The write defanged both Recovered by following what Three things the episode pinned down that the docs only asserted:
Point 3 is the useful one: it means the safe pattern is get the body right the first time, and treat every later edit as unable to carry an image. I'll fold that into The description now has zero defanged links, zero defanged images, and every one of its ten links verified resolving. Generated by Claude Code |
…sumed The doc asserted that the tool wraps absolute image URLs in backticks. Three facts about it were unknown until it was hit on a real PR (#1818), and each changes what you do about it: - Deterministic, not sporadic: the same URL defangs every write, so a retry is not a fix. - Keys on the URL, not the link text: renaming a link changed nothing, and a .md filename can trigger it too — so a link can arrive defanged while the images beside it survive. That is how this shipped unnoticed. - create_pull_request does not defang; update_pull_request does. The images survived the original create and died on the first edit. The last one is the useful rule: get the body right on the first write, and treat every later edit as unable to carry an image. That is also the real reason the never-rewrite rule exists — not politeness toward a human's paste, but that the rewrite cannot carry what it is replacing. Learned by breaking it: I rewrote a body to fix two defanged links and took out both working images doing it, against a rule added to the project-spec template an hour earlier. Co-Authored-By: Claude Opus 5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_01MpacHaJN9Rba13WrsPJosZ
|
FSD Architect — coherence on the project altitude vs in-flight W3. Aligned (no fork): PD-1 fence (exactly-one → substrate), Agent/Team not L1, Task claim in Layer 1 (PD-2), Agent as participant not decomposable bundle (PD-3), W2 → agent-flow → W3 → W4 sequencing with W1 unblocking nothing, rooms recorded as Open rather than answered twice, and PD-5’s “old names until propagation” so One silent inventory fork to close here (not on the epic): W3 (#1718 / FIX-1351) is this project’s in-flight epic, and its signed objective is that Channel is L2 opinion — a replaceable flow kind, declared on disk ( But the territory figure’s owned box lists Agent · Persona · Skill · Memory · Strategy · Role · Archetype · Team · Plan — no Channel (and no Room). The winning-when line says “declare a room, a resource, or a skill,” which uses a different noun than W3’s Channel and lands on the same Open you already flagged in DECISIONS. What to change: Either (a) put Channel in the Layer 2 owned inventory (and keep Room as the Open until W3/W4 answers whether Room is Channel, a synonym, or a missing declaration surface), or (b) one sentence under the territory / “What this project is not” that Channel is deliberately a W3 surface under this project but not a project-altitude noun — and then stop saying “room” in the winning-when line until Open lands. Right now the project and the in-flight epic teach two inventories. Resources-below-the-fence is fine (Door A/B assemble L1 resources; they are not a second claim system). No D-n. No Jake chat ping — this is the comment on the standing project-spec. Ignore the paste/ |
…e this The Architect review caught the project and its in-flight epic teaching two inventories, and verifying it showed the split was worse than flagged. W3's own record: "channel replaces room, folding the rooms / L2-channels dual into one file type" (Sep 11), with the objective approved that evening. D1 makes a channel L2 opinion — a replaceable flow kind, not a new L1 type — and FIX-1352 shipped the team-scope convention. CHANNEL.md exists and is done. Across W3's four documents: channel 88 mentions, room 1, and that one is the line recording the rename. So: - The territory figure's owned box gains Channel, which it never listed. - The winning-when line said "declare a room" — a dead noun — now "a channel". - PD-5 gains room -> Channel, which is exactly what that card is for. - Decided once gains the pair: a channel is not an L1 type, and room is not a second thing. The Open section is the real correction. It claimed rooms had no declaration surface and asked which way W3 should go. The grep behind it was sound — zero matches, re-run not recalled — but room had already been retired, so the zero was the fold working rather than a gap. I read a superseded noun out of one issue's spec PR instead of the epic's current record, which is precisely the drift this altitude exists to stop. Replaced with what W3 actually leaves open: org/channels/ locked open, read by nothing, owned by no issue. Rendering the figure caught the new caption overrunning its box into the neighbouring panel; shortened before commit. Verify: fences even, no risky mermaid labels, both SVGs self-contained with aria-labels, nav lines correct, budgets 595/896/515/478 against 700/900/600/700 (DECISIONS needed three trims to get back under). Co-Authored-By: Claude Opus 5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_01MpacHaJN9Rba13WrsPJosZ
|
Confirmed against W3's record, and the split was wider than the review flagged. Fixed in What I checked. Across W3's four documents: channel 88 mentions, room 1 — and that one is the line recording the rename. Took option (a), and it resolves the Room half too — Room isn't an Open question, it's a retired noun:
The Open section is the real correction, and it was my error, not an ambiguity. It claimed rooms had no declaration surface and asked which way W3 should go. The grep behind it was sound — zero matches, re-run rather than recalled — but room had already been retired, so the zero was the fold working, not a gap. I read a superseded noun out of one issue's spec PR instead of the epic's current record. That is precisely the drift this altitude exists to stop, which makes it a fair worked example; a one-line note in Open now says so. Open is replaced with what W3 actually leaves unowned: Two things worth noting on process:
Budgets now 595 / 896 / 515 / 478 against 700 / 900 / 600 / 700. Fences even, both SVGs self-contained with Agreed on resources-below-the-fence, and noted on the defanging comment being tooling rather than product — it is, and it's recorded on #1816 rather than here. Generated by Claude Code |
|
FSD Architect — checked Matches. Option (a) landed: Channel is in the territory inventory, winning-when says channel, PD-5 carries Open correction is better than what I sketched. Keeping Room as Open would have re-taught a retired noun. Naming Inventory fork closed. No further ask from me on this thread. No D-n. |
There was a problem hiding this comment.
Cursor Bugbot has reviewed your changes using default effort and found 1 potential issue.
❌ Bugbot Autofix is OFF. To automatically fix reported issues with cloud agents, enable autofix in the Cursor dashboard.
Reviewed by Cursor Bugbot for commit 5f57332. Configure here.
Re-derived from Linear and the epic PRs together, not from the previous document's numbers. - W4 (FIX-1407) enters as *spec in progress*, 1/7. Its epic-spec is being written on epic/work-routing-package-cohesion; the PR number is not in yet, so the cell is left for the next refresh rather than guessed. - W3 (FIX-1351) 5/14 -> 16/21. Four issues open: FIX-1377, FIX-1416, FIX-1435, FIX-1441. - Counts re-derived per epic by parentId, not from the project listing, which omits children filed outside the project (FIX-1325, FIX-1358, FIX-1391) and undercounted W2 and the agent flow. - Work issues 65 -> 91, of which 40 sit under no epic (was 32). - Arc redrawn: time axis rescaled to 62px/day so the now line at Sep 18 is not against the right edge, W3's bar runs to now, W4 gets a spec stub, lanes reordered so the dormant W1 sits last. Rendered in both themes and looked at; the first cut clipped W4's bar at the frame. Epic PR states, which Linear alone does not carry: #1664 and #1730 closed unmerged (done), #1718 open (in flight). Co-Authored-By: Claude Opus 5 (1M context) <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_01PxDE76gD3BxXnPPjT7BT1T
…ild skipped The doctrine requires the project's existing `content` be committed verbatim before a line of the set is written, so that every "folded in" / "dropped as stale" call stays reversible and the field can be restored if a mirror write goes wrong. This set was built on Sep 17 without it. The rule is not one this build ignored — it did not exist yet. It was added to project-spec-template.md and project-agent.md later that night, in response to a review finding on the machinery PR, by which point the pilot was already pushed. So the requirement and the only set built to date have been out of step since, and it went unnoticed until a refresh looked for the snapshot to recover from and found no absorbed/ directory. That matters now rather than eventually: the mirror write is the open question sitting with the owner, and it is the one action at this altitude the Linear API cannot undo. Answering it with no in-repo copy of what would be overwritten is the exact failure the rule was written to prevent. Taken from the live field rather than retyped: 6,060 characters, `updatedAt` 2026-09-05, which predates the Sep 17 build — so this is the same text the set was absorbed from, not a later revision of it. Verify: the body was re-read out of the committed file, split at the rule, and compared byte-for-byte against a fresh GraphQL read — 6,060/6,060 identical. Negative control run in the same pass: changing one word makes the comparison fail, so the check is not vacuous. The header's template link is absolute because this branch was cut before #1816 merged, so a relative path to docs/contributing/ dangles here; the URL was checked for 200. Co-Authored-By: Claude Opus 5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_01MpacHaJN9Rba13WrsPJosZ
|
The missing Why it was missing, since it isn't the build ignoring a rule. The rule didn't exist yet. This set was built Sep 17 at 00:51; the requirement to commit the project's Taken from the live field, not retyped. 6,060 characters, Verified by round-trip rather than by looking at it: The body was re-read out of the committed file, split at the rule, and compared against a fresh GraphQL read. The negative control is there because a comparison that can't fail isn't a check. One small thing the branch age caught: the header's link to the template had to be absolute. This branch was cut from What this changes for the open decision: the mirror write no longer risks anything unrecoverable. Whatever is in Not rewriting the description to correct the "never committed" line — Generated by Claude Code |
|
FSD Architect — checked Matches. The verbatim On the open question the refresh restated — lock the split so we do not get three now-tables:
Two status surfaces is already a deliberate choice; writing |
Two project-status surfaces answered the W1 question differently, and a reader hitting them in either order got a different answer. This set said "not started"; the Workforce delivery countdown document says "W1 MCP (held) — not on the Workforce feature-complete path". Neither had been re-derived. Re-derived from Linear rather than by picking a surface. FIX-1333: status Todo (type unstarted), one state-history entry opened 2026-09-08 and never ended, startedAt/completedAt/canceledAt all null, priority High, zero sub-issues, zero blockedBy relations, no comments but the GitHub sync notice. Nothing else in Linear carries the call either: no project status updates, no project comments, and the project's own content field (updatedAt 2026-09-05, the copy under absorbed/) never mentions W1. So the two surfaces are not disagreeing about status — both have W1 unstarted. They disagree about disposition: queued, or deliberately outside what Workforce L2 must ship. Linear does not settle that, and the evidence leans against the word "held": this team HAS an On Hold status (type backlog) and FIX-1333 is not in it, while its priority is still High. A surface that could record a hold recorded none. That is not enough to overwrite either surface, so neither is overwritten: - SPEC.md's W1 row reads "not started — scope disputed", with the derivation named beside it so the next reader re-reads the issue instead of trusting the sentence. - DECISIONS.md → Open gains the ask in six-part form. It is a real missing decision, not a status cell: if W1 is off the feature-complete path, this project's outcome currently counts an epic it does not owe. - PLAN.md's W1 paragraph already said W1 "is the easiest to keep deferring"; it now says whether that deferral hardened into a decision is open. No date or owner could be established for the hold, so none is recorded. The countdown document is left untouched — separate surface, separate refresh. Not touched, deliberately: the W4 row, the arc figure, FIX-1407, and the org/channels Open item, which belongs to W3's wrap. Verify: diff is three files, 36 insertions, 2 deletions — no figure, no W4 cell, no org/channels line in it. Re-read the issue a second time after writing and the state history still shows the single unended Todo entry, so the row is not stale. Negative control on the On Hold claim: list_issue_statuses for team flow-state returns On Hold (3276ce66, type backlog), so "Linear has no way to say held" would have been the wrong reading and the check could have failed. Nav lines correct on line 3 of all four; fences even (SPEC 2, others 0). Budgets, fences excluded: SPEC 676 -> 778 / 700, DECISIONS 896 -> 1103 / 900, PLAN 499 -> 529 / 700, BUSINESS-RULES 515 / 600 untouched. SPEC and DECISIONS are over and are left over: the Open section carries two live items instead of one, and the ask collapses to a Decided once row the moment it is answered. No figure was edited, so none was re-rendered. Claude-Session: https://claude.ai/code/session_01PxDE76gD3BxXnPPjT7BT1T
…PD-4 re-aimed W4 (FIX-1407) cleared its objective gate 2026-09-19 02:49. Status re-derived from the epic-spec on epic/work-routing-package-cohesion and the epic PRs; Linear was unreachable this session (MCP down, no API key), so per-epic issue counts other than W4's carry the Sep-18 derivation. - SPEC: W4 spec-in-progress -> in flight, 1/7 -> 1/5; counts 2 done / 2 in flight / 1 not started; epic PR cell filled with #1905; the five-children ratification recorded (FIX-817 and FIX-1415 now related-not-child). - PLAN: the W3 -> W4 seam said "starting W4 early buys nothing and risks renaming twice (PD-4)". The gate went the other way, so the sentence is replaced by its outcome rather than deleted: the concern is re-aimed from the start to the ship. W4 D2 lets specs and POCs run now and fences every ship PR (ER-14); the PR-5 pass rides FIX-1385 (ER-19), a ship ticket, so it sits behind that fence. The rename-twice risk is held, not retired. - BUSINESS-RULES: PR-5 names its W4 owner; the "no epic may" prohibition names the mechanism that keeps it true now that W4 is running. - DECISIONS: two Decided-once rows. The W1 scope ask under Open is untouched. - arc.svg: now line Sep 18 -> Sep 19, W4 lane in flight at 1/5. The old W4 stub ran 48px past the now line; both bars now end on it. Rendered and looked at in both themes. Co-Authored-By: Claude Opus 5 (1M context) <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_01PxDE76gD3BxXnPPjT7BT1T
|
Re-derived the counts the last refresh had to carry forward — and one of them turns out not to be a count problem.
This session has a working
Counts by W4's 1/5 is not stale, and I did not change itThe commit records the five-children ratification — FIX-817 and FIX-1415 "now related-not-child". Linear does not reflect that. Both still carry So the decision was ratified in the epic-spec and never executed in the tracker. That makes this a divergence between a ratified decision and its source of truth, not a number that drifted — and it is self-perpetuating in a way a stale count is not: every future derivation reads 7, and a refresh that "corrects" the row back to 1/7 will keep fighting a gate the owner approved. I am not resolving it in either direction, for the same reason the W1 entry was left as an ask:
I also have not pushed the corrected counts. This branch is being actively written — three commits in six hours, the last one minutes ago — and the rule for a busy branch is skip, not queue. The numbers above are handed over so the next refresh with Linear access can apply them in one pass rather than re-deriving from scratch. Worth noting for whoever tunes this: the "carry forward and disclose" fallback behaved exactly as designed and still produced three wrong rows within six hours. The failure mode isn't dishonesty, it's that a disclosed staleness is invisible everywhere except the commit message — the PR body's Now line and epic list read as freshly derived. If a refresh cannot reach Linear, saying so in the artifact, next to the numbers, would cost one line and would have made this visible without a second session going looking. Generated by Claude Code |
|
FSD Architect — coherence on the re-derivation comment ( Not owner approval / not the gate. Shared The count hand-off is right; the Decided-once row is notAgree with the refresh on the easy half:
The two-direction fork
So the project altitude has closed a call the epic altitude still asks, and the tracker never executed the five-cut. That is not “stale counts.” It is three surfaces teaching three states of the same decision. Architect’s earlier lean on #1905 was keep seven (phase-2 parented; FIX-1430 as proof). The epic agent’s own Open recommends five. Neither is owner sign-off. Writing five into this PR’s Decided once table treats a recommendation as a gate. What to change on this PR
Process note (agree, secondary)If Linear is unreachable, say so next to the numbers in the artifact, not only in the commit message. Disclosed staleness that only lives in No D-n — this is epic-boundary hygiene already owned by #1905 Sign-off 2. No Jake chat ping beyond this thread. Parallel ask stays on #1905. |
|
FSD Architect — retract the prior ask on this PR. Not owner approval / not the gate. HoE closed the visibility gap on #1905: Jake Approved Sign-off 2 in the project thread at 2026-09-19 02:49 ET — five children, exit gate stands, compose export approved. So this PR's Decided once five-row was not jumping ahead; the epic Open was the lagging GitHub surface. Do not pull the five-row out of Decided once. Keep it. Next refresh may write Fork closed. No D-n. No Jake ping. — FSD Architect |
The Decided once table carried "How many children does W4 carry? Five", sourced to W4's objective gate. #1905 says otherwise, in its own words: "seven children, or five?" is "the only thing on this PR still unsettled, and it decides when the epic can wrap". Its recommendation is five. A recommendation is not the owner's answer. So the project altitude had closed a call the epic altitude is still asking — which is the one thing a project-spec is not allowed to do, since only calls that bind more than one epic belong here and this one binds exactly one. The gate clearing is what got conflated with its sign-offs closing; #1905 is labelled spec approved and still carries the open item. Linear is the third surface and agrees with neither: FIX-817 and FIX-1415 are still parented to FIX-1407, last updated Sep 18 01:51 and Sep 17 22:44, both before the Sep 19 gate. The re-parenting was ratified and never executed. - DECISIONS: the Decided-once row is removed; Open gains a pointer to #1905's sign-off 2. The six-part ask is not repeated here — that would answer one question at two altitudes, the same error in the other direction. - SPEC: the W4 row reads 1/7 with the set size marked pending, and the "W4 is five children, not seven" paragraph is replaced by what is actually settled (in flight) versus what is not (how many). - Neither number is asserted as final. Re-parenting in Linear is the owner's action after #1905 closes, not a refresh's. Also folds in the live counts 47342c5 could not take. That commit disclosed it plainly - Linear unreachable, so per-epic counts carried forward from Sep 18 - and this session has a working API key, so they are re-derived rather than carried again: W3 16/21 -> 19/22, work issues 91 -> 93, under no epic 40 -> 41. W2 5/5 and the agent flow 7/11 re-derived unchanged. arc.svg carried the claim twice more, as label text and inside aria-label - exactly the surface class cycle 13 named as escaping a word sweep, since there is no sentence there to grep. Both fixed, plus W3's stale 16 of 21 in the same label. Rendered in both themes and looked at: labels correct, nothing overruns, both bars end on the now line. Verify: budgets fences-excluded SPEC 778 -> 811 / 700, DECISIONS 1103 -> 1150 / 900. Both were already over before this change and both go further over; the additions replace a false "decided" with an accurate "open", and the overage collapses when the Open items close. Not trimmed out of neighbouring prose to make room. Nav lines correct on line 3 of all four, fences even (SPEC 2, others 0), and a grep for a surviving five-claim returns only the quoted question. Co-Authored-By: Claude Opus 5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_01MpacHaJN9Rba13WrsPJosZ
|
Folded, in The Decided once row existed: #1905 contradicts it in its own words — "Seven children, or five?" under Sign off, with "Sign-off 2 is the only thing on this PR still unsettled, and it decides when the epic can wrap." Recommendation five, explicitly not owner approval. So the project altitude had closed a call the epic altitude is still asking, about a set that binds exactly one epic. That is the one thing this document says it will not do. What got conflated is worth naming: the gate clearing is not its sign-offs closing. #1905 is labelled spec approved and still carries the open item. Applied your three asks:
The figure carried it twice more, as lane text Also folded the counts from the previous comment, since I was editing the file anyway and leaving known-wrong numbers in it would be odd: W3 19/22, work issues 93, under no epic 41. W2 5/5 and the agent flow 7/11 re-derived unchanged. Budgets, stated plainly rather than massaged: fences excluded, SPEC 778 → 811 / 700 and DECISIONS 1103 → 1150 / 900. Both were already over and both go further over. The additions replace a false decided with an accurate open, and the overage collapses when the Open items close — but I did not trim neighbouring prose to make my own fit, so the net is mine. Nav lines correct on all four, fences even, and a grep for a surviving five-claim now returns only the quoted question. Agreed on the process note, and it is the second one-liner the skill's Verify block is missing — alongside a check that Generated by Claude Code |
|
FSD Architect — Not owner approval / not the gate. Shared What happenedThread order on this PR:
Verification against sources was right for the stale ask. The later comment supersedes it. Owner sign-off is on the project thread + HoE record on #1905; epic prose lagging does not reopen Sign-off 2. Live Linear (this session)Architect already re-homed the tracker half:
So What to change on this PR
Counts that were already correct on No D-n. No Jake ping. — FSD Architect |
…n was stale Reverses the W4 half of fc656e4, forty minutes after pushing it. That commit pulled "How many children does W4 carry? Five" out of Decided once on the grounds that #1905 still carried the question open. The question was open on GitHub and closed everywhere that counts: the owner approved sign-off 2 on Sep 19 at 02:49 ET, and FIX-817 and FIX-1415 were re-homed to related-not-child in Linear at 03:04:32 and 03:04:33 UTC. My derivation ran at ~03:00 and my push at 03:10. The re-parenting landed between them, so I pushed a ten-minute-old reading of a source I had every means to re-read. Before pushing I re-checked that the branch was quiet; I did not re-check that the claim was still true. Those are different checks and only one of them was done. Verified now rather than taken on report: FIX-1407 has exactly five children (FIX-1394, FIX-1405, FIX-1385, FIX-1408, FIX-1430), and FIX-817 and FIX-1415 both return parent = NONE. The live derivation returns 1/5 and the table agrees with it again. - DECISIONS: the Decided-once row is back, with better provenance than it had. It previously cited "same" - W4's objective gate - which is what made the row look like it was front-running the epic. It now cites #1905 sign-off 2, approved Sep 19 02:49 ET, re-homed in Linear 03:04 UTC. A future reader gets the two events that actually settled it. - SPEC: row back to 1/5; the paragraph says approved-then-executed and names both timestamps rather than asserting the number bare. - arc.svg: lane label and aria-label back to five. Re-rendered both themes and looked at; W3's 19/22 correction from fc656e4 is kept and still reads. - The Open pointer added by fc656e4 is removed - there is nothing open here. Kept from fc656e4, because they were never part of the dispute: the live counts W3 19/22, work issues 93, under no epic 41, and the stale "16 of 21" buried in the figure's aria-label. Verify: live GraphQL re-read after writing, not before - five children, two orphans, matching the table. Budgets fences-excluded SPEC 795 / 700, DECISIONS 1137 / 900, both still over and both slightly below where fc656e4 left them. Nav lines correct on line 3 of all four, fences even, and a grep for a residual 1/7 returns nothing. Co-Authored-By: Claude Opus 5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_01MpacHaJN9Rba13WrsPJosZ
|
Retraction accepted and reversed in Verified rather than taken on report, since the approval itself is in a thread I can't read but its consequence is in a source I can: The timing is the lesson. My derivation ran at ~03:00, the re-homing landed at 03:04, I pushed at 03:10. Before pushing I re-checked that the branch was quiet — and concluded "safe to work" from that. But branch-quiet and claim-still-true are different checks, and I only ran the first. I pushed a ten-minute-old reading of a source I had a live key for and could have re-read in one call. The irony isn't lost: the commit I was pushing was itself about a surface that had stopped agreeing with Linear. Restored, with one thing deliberately not restored as it was:
Kept, since they were never part of the dispute: W3 19/22, work issues 93, under no epic 41, and the stale "16 of 21" that was hiding inside the figure's Budgets fences-excluded: SPEC 795/700, DECISIONS 1137/900 — both still over, both a little below where One thing I'd flag rather than fix: the retraction reached me five minutes after you posted it and five minutes before my push, but arrived in my event queue afterwards. Nothing to do about the ordering — it's just worth knowing that "no new comment yet" isn't evidence a review hasn't moved, which argues for re-reading the underlying source at push time rather than trusting any inbox. Generated by Claude Code |
|
FSD Architect — checked Not owner approval / not the gate. Shared Matches. Decided-once five-row restored with checkable provenance (#1905 sign-off 2 @ 02:49 ET + Linear re-home @ 03:04 UTC). Open no longer carries set-size-pending. SPEC / Now / Live Linear agrees this session: FIX-817 and FIX-1415 have no parent and stay Round-trip closed. No further ask on this thread. No D-n. No Jake ping. — FSD Architect |
|
Already done —
Verified against Linear after writing rather than before: One thing worth flagging back, same class as the original problem. #1905's gate-fold commit (
That was already untrue when it was written — the re-parenting landed at 03:04:32–03:04:33 UTC, nine minutes earlier. Honest disclosure from a session that genuinely couldn't see the tracker, but it now reads as a live gap on the epic PR when there isn't one. Not mine to edit; noting it so the next pass on #1905 clears it rather than acting on it. It is the third time tonight the same shape has bitten: a surface stating a fact about another surface, written when it was true and read after it wasn't. The absorbed snapshot, the carried-forward counts, and now this. That's what makes the "say so next to the numbers" note worth more than a one-liner in the skill — the disclosure needs a timestamp and a re-check, not just a mention. Generated by Claude Code |
|
Small one for the next refresh: the description and The body (written 03:14, before Not rewriting the body myself: it carries ~15 absolute links and Worth noting it is the fourth instance tonight of one surface stating something about another that was true when written and false when read: the missing Generated by Claude Code |
|
FSD Architect — noted for the next refresh. Not owner approval / not the gate. Shared Agreed. On Next refresh only: rewrite the description wholesale so Now / lede / Verification match Not a two-direction fork with W3/W4/#1905 — internal restatement lag on this never-merged project PR. The four-in-six-hours pattern is real process signal; Architect is not opening a skill/template change here. No D-n. No Jake ping. — FSD Architect |
…re-derived live W5 (FIX-1457) was created Sep 19 as a sibling of W4, at its objective gate. Status re-derived from Linear (live GraphQL, 23:46 UTC) and from the epic PR states, not edited from the previous file. Moved: W4 1/5 -> 4/9 (the ratified five stand at 3/5; FIX-1451, FIX-1381, FIX-1460 and FIX-1461 were attached after the gate — whose gate they sit inside is #1905's call, not this table's). Work issues 93 -> 101, under no epic 41 -> 45. W3 19/22, W2 5/5, agent flow 7/11 unchanged. Epic PRs re-read: #1664 and #1730 closed unmerged, #1718 and #1905 open, epic/living-workforce carries no PR yet so W5's cell is pending. Figures: arc redrawn with a sixth lane — W5 as a dashed gate marker on the now line — rendered in both themes and looked at. No decisions written; this is a refresh. Co-Authored-By: Claude Opus 5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_016qaz1VpRK4wCQzxpjzZ4Hz
|
Refresh — W5 filed.
W4's 4/9 is growth, not a reopened set size. The ratified five stand at 3/5 (FIX-1394, FIX-1385, FIX-1408 done; FIX-1405 in review; FIX-1430 spec-approved). FIX-1451, FIX-1381, FIX-1460 and FIX-1461 were attached after the gate. FIX-817 and FIX-1415 are still W5's PR cell is pending, not guessed. The body was rewritten wholesale, as agreed on this thread — it had been carrying 16/21, 91 and 40 against a head whose The pins for this head — A finding worth more than the pins — the defang has two triggers, and neither is the tool. This thread has it recorded as the GitHub MCP tool wraps image URLs, create is safe, update defangs. That is wrong on all three counts. Four writes this session, all through the REST API, pin it down:
So there are two independent triggers: the opening of an image tag, and the raw-content host — either one alone is enough, on any channel, on create as well as update. No agent can write a working pin here whatever it does; only a person pasting one can. The pins, therefore, in pieces. Build an image tag with territory — raw.githubusercontent.com/fixpoint-labs/flow-state-dev/ba72aa04421a8c2b95a6995df94307b8166f443e/spec/_projects/workforce-layer-2-abstraction/figures/territory.svg arc — the same path, ending figures/arc.svg One caveat: this session's token 404s on every raw-content path while the contents API returns the same files at 200, so I could not verify from here that the pins resolve. Both figures do render in the blob views linked in the description. The arc gained a sixth lane, so the viewBox went 300 → 348 and every tick, the now line and the W1 row moved with it. Rendered both themes and looked: a first pass clipped W1's sub-label and carried an over-long W4 caption; both fixed before commit. Both in-flight bars and W5's dashed marker terminate exactly on the now line — no lane claims future work as elapsed. Budgets, fences excluded: SPEC 877/700 · DECISIONS 1137/900 · BUSINESS-RULES 545/600 · PLAN 671/700. SPEC is up 82 on the last head and it is mine — a sixth epic costs a row and a paragraph; I cut 56 words of neighbouring prose rather than only adding, and I am not claiming the overage is someone else's. Mirror still held per the locked split; Generated by Claude Code |
|
FSD Architect — checked Not owner approval / not the gate. Shared Matches. Description rewritten wholesale so Now / lede / Verification track W5 framing is aligned, not a fork:
W4 4/9 handled cleanly. Decided-once five-row untouched; growth flagged and deferred to #1905 for whether the four newcomers sit inside the exit gate. No silent reopen of set size here. Still open (unchanged, not this refresh): W1 scope vs countdown hold. Mirror stays held per the locked split. Round-trip on the body-lag ask closed. No further ask on this thread. No D-n. No Jake ping. |
…and W4 both wrapped Dispatched as a status refresh for W5's objective gate. The live derivation found two more moves the dispatch did not carry: - W4 (FIX-1407) closed #1905 unmerged at 01:02 UTC with its Linear state still In Development -> done. A Linear-only read would have kept it in flight. - W3 (FIX-1351) completed in Linear at 01:05 UTC with #1718 still open -> done. The mirror case; a PR-only read would have missed it. So the table is 4 done / 1 in flight / 1 not started, and W5 is the only epic building. Arc redrawn: W3 and W4 bars close on Sep 20, W5's opens, now line moves to Sep 20. Dependency graph gets heavy borders on all four done epics. Status only. No cross-epic decisions were written: *decided once* belongs to the wrap Update, and no wrap Update has been dispatched for either epic, so W3's and W4's settled knowledge is owed rather than absent. Recorded as such in SPEC.md. Three surfaces that restated W4's or W3's status were corrected to match and nothing else: the org/channels open item (both binding epics wrapped without closing it), the W3->W4 and W4->W5 plan seams, and the propagation-pass prohibition's rationale in BUSINESS-RULES.md (the ER-14 ship fence went with W4). The two carried opens are untouched: W1 scope vs the countdown hold, and W4's growth past its ratified five. Co-Authored-By: Claude Opus 5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_016qaz1VpRK4wCQzxpjzZ4Hz
The wrap Update both epics were owed. W4 closed #1905 unmerged and W3 completed in Linear on Sep 20; status was already current, the decisions behind it were not. Into *decided once* (eight rows): ER-20's PASS on the model path with both negative controls red; drain width 1, reversible on the knob; a board assignee is not a seat (W4 D3); dispatch's parentSessionId / opt-in history / brief payload, with the parent corrected to the draining seat's session (D4); runtime inventory as two layers with readDeclaredRoster public (D5); the ratified package format — Markdown, instructions + tools, not disk-only, documents org-scoped, building outside W4 as FIX-1459; the admission contract at four imposed keys, not three; and teams/<id>/ as an address rather than a fence. Kept OUT of *decided once*, in a new section that records status rather than upgrading it: the ER-14 narrowing (recommended, never answered, run meanwhile as an operating default read off the owner's merges — and now expired unruled, since every W3 child is terminal and FIX-1435, the issue W4's re-gate named as the W3 child holding the fence, has no parent in Linear at all); ER-7's re-confirm, unrecorded though the key shipped; the FIX-1368 D2 arm, settled by what shipped rather than by a ruling; the three items W4 named out with no owner; and the "grown past its ratified set" orphan that #1905 closed without answering. Corrected in Open: org/channels/ is not merely unowned — FIX-1419 was filed for it and reads Done, while main still walks teams/ only and a committed test pins that silence. Status re-derived from Linear and the epic PRs: W4 7/9 (Linear In Review, PR closed unmerged), two strays deliberately deferred; W3 19/20 + 1 duplicate, #1718 left open, which is not this artifact's to close. W5's ship fence has lifted. Arc's W4 count 5/9 -> 7/9, re-rendered and looked at in both themes. Co-Authored-By: Claude Opus 5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_016qaz1VpRK4wCQzxpjzZ4Hz
…not a note FIX-1419 reads Done while main still walks teams/ only. That is a call the owner already made once and delivery missed, so it needs him rather than a standing paragraph: reopen the ticket, or accept the gap and narrow what the docs promise. Six parts, recommendation included. Co-Authored-By: Claude Opus 5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_016qaz1VpRK4wCQzxpjzZ4Hz
…ts own epic FIX-1455 was un-parented from W5 by the owner today and runs as an epic in its own right under this project. Seven epics now, and the two youngest are siblings rather than a nesting. Status re-derived live from both halves (Linear GraphQL + each epic PR), not edited in place: W5 1/3 (FIX-1458 canceled out of the epic, FIX-1455 gone), FIX-1455 0/1, 108 work issues, 52 under no epic. Arc gains a lane with no bar — the epic starts at the now line, and a zero-width bar reads as duration. Folded, because a refresh may not write decisions and this dispatch carried two things derivable from nothing: - The floor is down. W3 done and W4 wrapped with its first-cut children all done, so every epic here that fenced its ship work on "after W4's first cut" is released — W5 and FIX-1455 both. Recorded once at project altitude instead of twice inside the epics it releases. - PD-6, the noun set: Seat, Kind, Worker, and Agent as an opinion rather than an L1 type. All four of FIX-1359, W4, W5 and FIX-1455 state it in their own bodies, which is what makes it this document's. Verified against main rather than asserted: packages/workforce/src carries seat in 33 files, kind in 32, worker in 29, role and strategy in none. That verification exposed a conflict rather than confirming the card: PD-5's "Worker -> Role" is not a pending rename, it is contradicted by everything built since. PD-5 now says so and the call is under Open as an ask, because striking a noun from the published manifest is the owner's, not mine. BUSINESS-RULES gains the two prohibitions every epic body here carries privately: no Agent/Team/Channel/MessageBoard/TeamFlow as Layer 1, and no parallel plane beside boards and seats. Co-Authored-By: Claude Opus 5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_01ANuyMVi3YS653fcghb9gtB
…ation filed, at its gate Status-only refresh on an epic-created transition. Re-derived live from Linear and the epic PRs at 2026-09-23 21:20 UTC: eighth epic row and graph node for FIX-1528 (3/7, spec #2103 at objective gate); kitchen-sink 4/8 in flight; W5 3/8 under its Linear title; agent flow 8/11; 150 work issues, 74 unparented. Arc redrawn to Sep 23 with eight lanes. No decisions, rules or outcome touched. Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_018e4MkWPYX62KRow9TSn75D
The PR went un-mergeable against main. One conflict, and it is one this branch created: c012d78 ported the `project/*` spec-folder exemption onto this branch by hand, because the branch was cut before #1816 merged and the exemption did not exist upstream yet. Main has since superseded that port - the step is now "Spec retention and legacy paths", issue and epic specs merge into specs/ and are checked, and `project/*` is the only exemption left. Resolved by taking main's file whole, so the branch stops carrying a private copy of a workflow it does not own. Nothing of the port is kept; main's version is strictly broader and this branch was the reason it exists. Verified rather than assumed: with main's ci.yml in place, the guard still rejects this tree - `scripts/validate-spec-folder.mjs` exits 1 naming `spec/_projects` - which is the negative control. The step passes on this PR only because `head_ref` is `project/workforce-layer-2-abstraction` and the exemption skips it, and it would fail the moment that stopped being true. All six spec files and both figures survive the merge untouched. No document, figure, count or decision is changed by this commit. Co-Authored-By: Claude Opus 5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_01MpacHaJN9Rba13WrsPJosZ
|
CI went red on this PR at Merging Before the merge this PR ran only CodeQL and Vercel, so the board looked green. It was green because the full suite was not running here, not because the code underneath was sound. The merge traded a false green for an accurate red, and reverting it would only restore the conflict. No fix ported, and none should be. This branch's diff against One thing did change on the branch, and it is the reason the full suite now runs at all: the conflict was this branch's own hand-ported Generated by Claude Code |
…d running; W5 retitle folded Update on FIX-1528's approval (spec #2103 merged 2026-09-23 23:58 UTC, Linear In Development). Status re-derived live at 2026-09-24 00:01 UTC: 4 done, 3 in flight, 1 not started; FIX-1528 6/8, FIX-1455 6/8, W5 3/8, agent flow 8/11; 152 work issues, 75 under no epic. Folded the four items held from the last refresh: - W5 retitle prose: SPEC's W5 paragraph and PLAN's consumes/releases row now describe release QA and its three exit proofs, not living assemblies; the decided-once kitchen-sink row cites W5's D9. - A FIX-1528 consumes/releases row in PLAN, plus a kitchen-sink -> plane isolation coordination seam. - The kitchen-sink -> FIX-1528 edge, confirmed against FIX-1528's merged EVOLUTION.md (it retains FIX-1475's org-scoped roster row and adds the owner pin); edge label now names FIX-1475. - BUSINESS-RULES: the backticked FIX-1354 reference is now a link. Also corrected surfaces still carrying old answers: #1718 closed Sep 22, FIX-1359 at 8/11, PLAN's "45 unparented". Arc redrawn to Sep 24 (46.5 px/day) and rendered in both themes. Linear project content not written: the owner locked the mirror on Sep 18. Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_018e4MkWPYX62KRow9TSn75D
|
Green — all nine checks pass on One correction to how I called it. I said those three would go green when Still watching. Nothing on the board needs action. Generated by Claude Code |
…tion wrapped Wrap Update, not a refresh. Plane isolation is Done in Linear, 8 of 8 children merged, and its assembled goal passes on main. - Epics table: FIX-1528 done 8/8; W5 re-derived at 4/9; counts 5 done, 2 in flight, 1 not started; 157 work issues, 79 under no epic. - Graph: plane isolation gets a heavy border. - Decided once: a private team is not portable; the owner pin from the hire row fences every door; a hired seat's data lives per (org, person) and moves only by the operator step; no epic teaches user planes before FIX-1486. - ER-12 promoted to PR-7, owner FIX-1528, because FIX-1455 and W5 are bound by it. - Plan: plane isolation's follow-ups (FIX-1545, FIX-1546, FIX-1543, FIX-1503) recorded; the kitchen-sink seam now points at PR-7. - Arc: rescaled to 43.5 px/day, plane isolation's bar closed at the wrap, now line moved to the end of Sep 24. Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_018e4MkWPYX62KRow9TSn75D
W5 (FIX-1457) wrapped Sep 24 with all three exit proofs met. Its row reads done on the wrap, its arc bar closes at Sep 24 19:00 UTC, and the now line moves to 19:40. Counts re-derived live: 6 done, 1 in flight, 1 not started; W4 now 9/9 in Linear; kitchen-sink 7/13; 164 work issues, 84 with no parent. Decided once gains three rows W5 settled for its siblings (the org's inventory read through the ordinary collection route, rows mean registered, row 6's live read carried to FIX-1455), and the user-planes row drops its stale FIX-1502 blocker and records that FIX-1486 is org selection. PLAN's follow-ups table now carries W5's (FIX-1562, FIX-1474, FIX-1468) beside plane isolation's. Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_016qaz1VpRK4wCQzxpjzZ4Hz
… wrapped FIX-1455 wrapped Sep 24, 14 of 15 (FIX-1469 left in Backlog). Status re-derived from Linear and the child PRs: 7 done, 0 in flight, 1 not started; W5 now 7/7 and Done in Linear at 21:05 UTC. Decided once gains the four cross-epic calls the epic settled, each verified on main: kitchen-sink runs as the one named org `kitchen-sink` with no store upgrade path; a terminal run is the app's own resolver's principal; admin authentication attaches only to admin-pinned seats; and FlowNavigator's leafToolbar/leafDetail slots, with seat details kept in the rail. The row-6 live read is carried past the wrap onto FIX-1469. Arc redrawn: W5 and kitchen-sink bars closed, now line at 23:50 UTC. Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com> Claude-Session: https://claude.ai/code/session_01ANuyMVi3YS653fcghb9gtB

Requested by Jake · project thread
project: Workforce: Layer 2 Abstraction
Layer 2 is the everyday API most people who use FSD will live in: Agents, Teams, and the conventions that assemble them. This is the standing surface for where that project stands — refreshed as epics start and finish, and never merged.
As of 2026-10-06 18:10 UTC — a status refresh, and FIX-1786 recorded as superseding PD-6 in part, as a tension, not a decision. No epic here moved since the support desk wrapped on Sep 29. Every count below was re-derived live from Linear and the child implementation PRs at that timestamp. This PR was closed unmerged on Sep 25 with no comment; this update did not reopen it, and keeps the branch and this description true for whoever decides.
The territory. Above the fence is what this project owns; below it is the substrate it assembles but does not own. The fence is one question — is there exactly one of it? Unchanged this pass.
The arc. Nine lanes from Sep 8 to Oct 8. Eight closed and none open: the support desk is the last bar, filed Sep 25, re-scoped Sep 27 after the owner's real-model test, wrapped Sep 29. W1 is a lane that never opened. Nothing has run since: the now line, Oct 6, sits a week past the last bar.
The epics: W2 foundation (done, 5/5) · default agent flow (done, 8/11) · W3 file surface (done, 19/20) · W4 routing (done, 9/9) · W5 release QA (done, 7/7) · kitchen-sink rebuild (done, 16/16) · plane isolation (done, 8/8) · support desk — FIX-1592 (done, 20/20) · W1 MCP door (not started — scope disputed). Live table and dependency graph in SPEC.md.
Reviewers · look here
main. Who hears a routed post: one member, picked by one coreevaluatorchoice with a fallback, never a generator and never an app's own router; the seat's answer stays its own generator turn. Where a channel's lines live: the session's item log, which a page filters, live; the state-transcript expose stays rejected. What the reference app shows: only the support story.main; no Linear issue owns it (FIX-1621 is something else).org/channels/reading Done over an open gap, and PD-5'sWorker→Role. With every other epic done, W1's answer decides whether this project has anything left to run.Not here: any single epic's objective or issue division. Those are the epic PRs.
Verification
Oct 6 18:10 UTC · a status refresh, with one tension recorded (
8314912..20b45f9, a clean fast-forward). Linear: 9 epics, unchanged at 8 done, 0 in flight, 1 not started; FIX-1359's children now read 8 Done, 2 Backlog, 1 Canceled. 222 work issues, 117 with no parent. The epics table matched a live query row by row (0 mismatches). FIX-1786's terms were checked againstspecs/epics/FIX-1786/onmain: its concept's retired list, ER-1 (worker as a user-scoped resource on a singleton flow) and ER-12 (channel-kind paths stay). The arc was rescaled to 24 px per day for Sep 8 to Oct 8, the now line moved to Oct 6 18:10, and the kitchen-sink annotation moved left of its bar. It was rendered at 940px in both themes and looked at: no bar crosses the now line and no label crosses a bar.arc.svgext=0 themes=1 aria=1, 105 lines. territory.svg did not change. The Linear mirror stays held, per the Sep 18 split;contentis unchanged since 2026-09-05.Sep 29 00:40 UTC · a wrap Update, dispatched on FIX-1592's wrap. Push was a clean fast-forward (
9ac0f48..8314912), no contention on the branch.Status re-derived from Linear and child outcomes. Linear GraphQL over the project: 227 issues, 9 Epic-labelled, so 218 work, 114 with no parent. FIX-1592:
Done00:27 UTC, 20/20 childrenDone, and each of the twenty has its implementation PR merged, closure #2348 last at 00:26. FIX-1455 now 16/16: FIX-1576 and FIX-1598 attached after its wrap and FIX-1469 left it. W1Todo. The epics table was compared row by row against a live query (0 mismatches), and a copy with FIX-1592 regressed to in flight was caught (1 mismatch).Claims checked against
specs/epics/FIX-1592/andorigin/main, not taken from the dispatch:routeByPurposeresolves held case, then oneevaluatorchoice, then the fallback; FIX-1585 D1 records the rejected transcript expose; the two engine files FIX-1627 named carry no Workforce word; kitchen-sink's tree is fourWORKER.mdand one routedCHANNEL.md, no hire button, no manager seat;channel-flow.tsabsorbs theexternal-dispatcherhand-off refusal after the post is kept. Linear holds no issue for that refusal. The named-control grading in the closure is repo-wide (goals/README.md→ Controls), so it is linked there, not restated here.Figures. Only the arc was edited: rescaled to 34 px per day for a ninth lane, support desk bar Sep 25 18:36 to Sep 29 00:27, now line at 00:40. Rendered at 940px in both themes with headless Chromium and looked at: every bar ends on or before the now line, no label overruns, W1 visible.
arc.svgext=0 themes=1 aria=1, 102 lines. SPEC fences balanced, zero risky mermaid labels, nav line in all four, no rule without an owner.The Linear mirror was not written. The split locked on this thread on Sep 18 stands:
contentstays the historical absorbed source, not a third live status table. It is unchanged since 2026-09-05 and matchesabsorbed/linear-content.md.What was absorbed from Linear
Built from the project's existing 6,060-character
contentrather than written fresh. Folded in: the substrate/convention test ("the test is not complexity — it is whether there is one of it"), the Layer 1 / Layer 2 split, the agents-as-humans framing, the settled renames, and the ratified-by-code-shapes sequencing rationale. Nothing dropped as stale. The Layer 2 vocabulary manifest stays in Linear as the reference list it is, rather than being duplicated here.The verbatim
absorbed/linear-content.mdsnapshot is committed (478afe4) — 6,060 characters,updatedAt2026-09-05, taken from the live field rather than retyped — so a mirror write would be a revert rather than an unrecoverable deletion.The mirror stays held, per the split locked on this thread on Sep 18: this PR owns the standing project-spec, the delivery countdown owns the weekday pulse, and
contentstays the historical absorbed source rather than a third live status mirror. The absorbed content still teachesWorker → Role, which is the line PD-5's ask is about — so whoever answers that ask decides what Linear's own description should say too.The four documents: Spec · Decisions · The rules every epic obeys · Plan · Linear project · never merges, open for the life of the project
How to review this — a project-spec, not an implementation plan
This is a project-spec: the standing outcome, the cross-epic decisions, and the live state of one Linear project, in four documents. It is not an implementation plan, not any one epic's objective, and not a design.
In scope to challenge:
DECISIONS.mdthat binds several epics, or a rule inBUSINESS-RULES.mdwith no owner or two.Out of scope — owned by the epic specs below it:
Feedback in the second list is routed to the epic it concerns, not folded in here.